Well seems like the problem is now solved and I have started filling Pond #1 for the second time.
I need some advice and discussion of the following structures ...
A = Pond #3 - 45,000 litersThe primary purpose of this pond will be to act as a vegetation filter and have some goldfish and maybe some kurpers in. The fish is obviously for the insects and whatever food happens to be there but will also be the decoy to attract the predators and hopefully keep them away from the Koi.
B = Weir structureThis was done so that the bottomdrain is protected from the obvious potential of catching rotting leaves that will land in the pond from mostly the inhabitants of the pond. It was also done so that water can flow freely without floating plants choking the spillway.
C = Surface skimmerThis is where surface skimming for pond #3 happens and the gate can be closed at will. The box is divided in two C/D with C having 3 layers of concrete stone in Avocado bags. Water filters through the stone and then out into D. I am confident that all plant material will be trapped here that is drawn off by the skimmer.
D = Settlement chamberNot much to say about this one.
E = Course filtrationAll water drawn off the whole system will land here on it;s way back to the pump pit. This box also contains 3 layers of bagged concrete stone. The spill drop is fairly high so a lot of aeration takes place here.
F = Settlement ChamberThis box is connected to the pump pit in a way that the water level will not fall below the surface of the bagged stone in E.
G = Pump pitThis pit is 2 meters deep and holds around 2,500 liters of water. It was built after I realised that that E and F could not cope with the "transit" volume of water.
From the pump pit water will be pumped through two 1,000 liters tanks that will each contain 300 liters of bio - balls and from the tanks it will flow by gravity over the primary inlet into Pond #1.
I am now thinking of hanging bio brushes in F and D.
I have also found a source for oyster shells and I am planning on bagging them an place them in the bottom of F and D.
My question is this ...
How will you employ the above setup if it was your system ... what other filtration material will you use and wat plants will you add and where.
Thanks.
Plants in here are ...
Palmiet, Papyrus and Vark ore.